District Collector Abhay Verma reviewed the progress of construction works of additional rooms and other development works under the National Middle School Education Campaign and Education for All programme.
In review meeting, the Collector has given instructions to officials to speed up the pending works and to complete it on priority. The meeting was organised at Collectorate conference hall, on Thursday.


He instructed the assistant engineers and deputy engineers to issue completion certificate of the construction work by June 15, 2018 compulsorily, and if the work not completed with in the stipulated time then strict action would be taken against related construction agencies, Assistant Engineers and Deputy Engineers.


He also warned to take strict actions against those Deputy Engineers whose 5 or more than five development works are not completed on time as well as warned Deputy Engineers to stop their 7 days salary.


He also gave instructions to take against President and Secretary of Primary School of Heengpani for not getting the development work done pending since 2005-2007. In this series he suspended the Secretary, Assistant teacher of School Management, Garibar Singh Mehra. During the meeting, while reviewing the development work under National Middle Education Campaign, expressed dissatisfaction on agency PIU for sub-standard construction work, therefore he instructed then agency to complete the construction work as per quality norms and with in stipulated time. He also ordered inquiry in the carelessness paid the construction work by PIU. Instructions were also given to the divisional Project Engineer, PIU to complete the construction work in Government high schools of Kunda Chota, Chheetapur, Heerapur, Chawarpatha development block, Usari, Bairagarh and other places.


He asked the deputy engineers to ensure and submit the attestation to the District Education Centre related to the completion of development work before the next meeting, along with this he asked them to submit the application and photo to the Jila Panchayat, for the cases related to RRC. Amongst those present in the meeting were DSP SK Koshti, SDPC GS Patel along with BRS, Assistant Engineer MANREGA and Deputy Engineer.